How Long Does an Apartment Renovation Take in Israel? Real Timelines from 8 Projects
Updated: Nov 9
In my projects, a full apartment renovation in Israel usually takes two to six months of planning and three to six months of works. A private house, or a new apartment customized before construction, takes longer: MG House needed 10 months of planning and 8 of works, and the C apartment followed a 24-month building schedule.
By Maya Sheinberger | 13.10.25
"How long will it take?" is the first question every client asks. The honest answer depends on the size of the home, how much changes and how well the planning is closed before the works start. Here are the real numbers from my projects.
Key takeaways
Count planning and works separately: in my projects, planning alone takes two to twelve months.
An apartment renovation usually takes three to six months of works.
A private house with permits takes longer, because the permit is part of the planning.
In a new building, the timeline follows the construction of the building.
The best way to keep to schedule is to order everything before the works begin.
Real timelines from my projects
Project | Type | Planning | Works |
B, Tel Aviv | Holiday apartment, 105 sqm | 2 months | 3 months |
N, Tel Aviv | Apartment, 67 sqm, stripped to the shell | About 3 months | About 5 months |
S, Hod Hasharon | Apartment | 3 months | 5 months |
RB, Tel Aviv | Apartment, 100 sqm | 3 months | 6 months |
M, Tel Aviv | Penthouse on two floors | 5 months | 4 months |
V, Tel Aviv | Holiday apartment for an overseas client | 6 months | 6 months |
MG House, Hod Hasharon | Private house with a new attic | 10 months, including the permit | 8 months |
C, Tel Aviv | New apartment, 120 sqm, planned before construction | 12 months | 24 months (the building's construction) |

Why does planning take as long as it does?
Planning includes the layout, the electrical and plumbing plans, the joinery, and choosing every finish, fixture and piece of furniture. In the M apartment, planning took five months and the works only four, because all the planning and orders from suppliers were closed in advance, so we could start the moment the keys were handed over. I tell the whole story in my penthouse renovation case study. In the S apartment, we started the works only after everything was ordered, and there were no moments of crisis along the way.
Why do some projects take longer?
A permit. In MG House, the 10 months of planning included the building permit for the new attic floor, and the renovation itself took eight months.
A new building. The C apartment was designed and customized before the construction of the building began, so its 24 months follow the building's construction, not a renovation crew. Read more about customizing a new-build apartment.
A client who lives abroad. In the V apartment, the owner lives in London. Planning was done by email, and we gathered all the meetings, material choices and furniture orders into a single week of her visit. I wrote about this way of working in renovating a Tel Aviv apartment from abroad.
The unexpected. In the same project, the building's large elevator was out of order for two weeks and delayed the start, and several people on the team were injured or fell ill during the works. Every project needs a little room in the schedule for things no one can plan.

Why don't small apartments always take less time?
The N apartment is only 67 sqm, but it was stripped down to its shell, including the windows, the flooring and the old drywall ceilings, so it needed about five months of works. The amount of change matters more than the size. The B apartment, at 105 sqm, took three months of works: the owners asked to keep the existing layout, no walls were moved, and the new herringbone parquet was laid over the existing floor tiles.

How to keep a renovation on schedule
Close the planning before you start: drawings, finishes and furniture.
Order long-lead items early: joinery, windows, kitchen and lighting.
Have one person manage the project, the designer, a supervisor or someone you trust.
Keep decisions with one or two people, and make them on time.
Leave a buffer for the unexpected.
For a calmer process overall, read my post on fearless renovation, and if you are renovating as a couple, how to finish the process still in love.

Frequently asked questions
How long does it take to renovate an apartment in Israel?
In my projects, usually two to six months of planning and three to six months of works for an apartment.
How long does it take to renovate a private house?
Longer. MG House needed 10 months of planning, including a building permit for an attic, and 8 months of renovation.
Does planning take longer than the renovation?
Sometimes. In the M apartment, planning took five months and the works four, because everything was closed before the start.
Can I renovate while living abroad?
Yes. In the V apartment, planning ran by email and all meetings and choices were gathered into one week of the owner's visit; planning and works took six months each. More in renovating a Tel Aviv apartment from abroad.
What delays a renovation the most?
Decisions that are not closed in time, items ordered late, permits and the unexpected, like an elevator out of order.
Planning a renovation and want a realistic timeline? I'd love to hear about your project.
Maya Sheinberger is an interior designer with more than 17 years of experience. After five years at a leading architecture firm, she founded her independent studio in 2012. She holds a B.Des with honors from the College of Management. Her work has appeared in more than 150 publications in Israel and abroad, including eight Archilovers Best Project awards, and one of her apartments features in the book The New Minimalist Style.
Photography @itaybenitphotographer, V: Shai Epstein · Styling @maya_livnat_harush, V: @ofri.paz






