What Does an Interior Designer Do? The Interior Design Process, Step by Step

Aug 2
5 min read

Updated: Nov 9

An interior designer turns your needs into a complete plan for the home: the layout and furniture plan, working drawings for the contractor, finish materials, the kitchen, custom joinery, lighting and furniture, and then visits the site to check that everything is built as designed. In my studio, the process runs in two stages, from the first layout to the final styling.


By Maya Sheinberger | 03.08.26


Many people imagine that an interior designer mostly picks colors and cushions. In practice, most of the work happens long before anything is bought, in drawings that decide where every wall, socket, cabinet and light will go. Here is how a full project runs in my studio, stage by stage, so you know what to expect before you start.


Key takeaways


  • The process starts with a needs assessment, not with materials.

  • The furniture layout is the first and most important drawing. Everything else follows it.

  • Working drawings tell the contractor exactly what to build.

  • Materials, kitchen, joinery and lighting each get their own planning stage.

  • Site visits make sure the drawings become reality.


What is the interior design process?


The interior design process is the sequence of planning stages that takes a home from an empty or outdated space to a finished one: understanding the needs, planning the layout, preparing working drawings, choosing materials, designing the kitchen and joinery, planning the lighting and furniture, and supervising the result on site.


How does a project start?


Every project starts with an in-depth conversation about how you live: who lives in the home, how you cook, where you work, what you store and what bothers you today. From this, I build a design program, a list of needs and wishes that guides every decision later. If it's a new-build apartment, you also need the existing plans from the developer, ideally as DWG files, so the planning starts from accurate drawings.


The furniture layout plan of the OA apartment, with the kitchen island, living area, bedrooms and bathrooms drawn in.
The furniture layout plan of the OA apartment, with the kitchen island, living area, bedrooms and bathrooms drawn in.

What are the stages of the design?


Stage

What you get

Layout and furniture plan

The division of the spaces and where every piece of furniture goes

Working drawings

Construction, furniture layout, electrical and lighting, ceilings and air conditioning

Finish materials

Tiles, wall cladding, sanitary ware, worktops and doors, chosen together with you

Tiling plan and elevations

Wall elevations of the bathrooms and kitchen, and a floor tiling plan

Kitchen

Kitchen design and coordination with the kitchen company or carpenter

Consultants

The kitchen, air-conditioning, electrical, plumbing and underfloor heating plans integrated into the design

Site visits

Checking the work against the drawings, and solutions when the site needs an adjustment

Joinery

Bathroom cabinets, bookcases, wardrobes, wall cladding, hidden doors and special pieces

Lighting

A lighting plan and help choosing the fixtures

Furniture and styling

Loose furniture, curtains and rugs


In my studio, the first seven rows are Stage A and the last three are Stage B.


How long does each stage take?


In my current proposals, the furniture layout is ready within about 10 business days of approving the proposal and receiving the existing plans as DWG files. Choosing the finish materials takes up to about 20 business days, depending on how quickly decisions are made. The electrical, lighting, plumbing and ceiling plans take up to about 20 business days after the layout is approved, and the tiling plan and bathroom elevations about 10 more after the materials are chosen. For how long the whole renovation takes, see my guide to how long a renovation takes in Israel.


How are materials and furniture chosen?


Together, in focused meetings. I prepare a recommendation before most meetings, so we look at a short list of options that already fit the plan instead of wandering through a showroom. That's also where most renovation mistakes are avoided, as I explain in my post on questions to ask in every showroom.


The AA apartment kitchen, with dark gray tall cabinets and open shelves, and a terracotta pendant in the foreground.
The AA apartment kitchen, with dark gray tall cabinets and open shelves, and a terracotta pendant in the foreground.

What happens during construction?


I visit the site at key stages, which are scheduled according to the building stages and the contractor's needs. On each visit, I check that the work matches the drawings and solve what the existing site requires. Phone and video calls run throughout. In the AA apartment, for example, the custom entrance cabinet had to wrap a structural column and still hold a washing machine and a dryer, the kind of detail that is drawn in the planning and checked on site.


The BN apartment kitchen, with a marble-look island, black bar stools and open shelves on the back wall.
The BN apartment kitchen, with a marble-look island, black bar stools and open shelves on the back wall.

What is usually not included?


I accompany the project from the concept to the end of the works, including ongoing guidance with the contractor, consultants and suppliers. Construction management itself, procurement, bills of quantities and building permits are not part of the design service, and the client contracts the contractor and suppliers directly. Consultants are engaged separately, and I integrate their plans into the design. Renderings are optional. It's worth knowing this from the start, so nothing falls between the chairs.


Frequently asked questions


Do I need an interior designer or an architect?

For changes inside an existing home, an interior designer usually leads the planning. Structural changes and permits need an architect or engineer. I wrote more about it in interior designer or architect.


When should I hire an interior designer?

Before the works start, ideally before you buy materials or sign with a kitchen company. In a new-build apartment, before the developer's deadline for buyer changes.


Does the designer manage the contractor?

I work alongside the contractor throughout the project: I visit the site, check the work against the drawings and answer the contractor's questions. Construction management itself is a separate service, and the contract stays between you and the contractor.


What does the furniture layout include?

The division of the spaces and the position of every piece of furniture, based on the needs assessment. It's approved before the working drawings start.


Planning a renovation and want to know how the process would look for your home? I'd love to hear about your project.


Maya Sheinberger is an interior designer with more than 18 years of experience. After five years at a leading architecture firm, she founded her independent studio in 2012. She holds a B.Des with honors from the College of Management. Her work has appeared in more than 170 publications in Israel and abroad, including eight Archilovers Best Project awards, and one of her apartments features in the book The New Minimalist Style.