Renovation Order of Works: A Step-by-Step Checklist for Your Home

Jul 26
4 min read

Updated: Nov 9

A home renovation should follow a fixed order: planning and ordering first, then demolition, infrastructure, ceilings, floors, joinery and finishes, and only at the end furniture and styling. The most important step comes before the first hammer: close the planning and order everything in advance, so each team can work without waiting for decisions.


By Maya Sheinberger | 27.07.26


Many renovation crises start when the order breaks: a decision made too late, or a material that cannot reach the site. In the S apartment, closing every detail in advance meant there were no hard moments of crisis. Here is the order I follow, with lessons from my projects.


Key takeaways


  • Close the planning and order the finishes before the works start.

  • Expect surprises at demolition and leave room for them.

  • Infrastructure comes before ceilings, and ceilings before floors.

  • Check that large materials can actually get into the building.

  • Furniture and styling come last, when the dust is gone.


What is the right order of works in a renovation?


Step

What happens

Lesson or rule

1. Planning

Layout, electrical and plumbing plans, joinery, finishes

M: planning and orders were closed before the keys

2. Permits

Only when needed, for example adding a floor

MG House: the permit was part of 10 months of planning

3. Ordering

Finishes, furniture, kitchen, long-lead items

S: works started only after everything was ordered

4. Demolition

Removing what is replaced

N: stripped to the shell, surprises appeared only then

5. Infrastructure

Electricity, plumbing, air conditioning, by licensed professionals

N: concrete beams dictated the AC route

6. Ceilings

Lowered ceilings, lighting, AC pipes

S: an 8 cm uniform lowered ceiling

7. Floors

Leveling, then the floor finish

N: the first tiles chosen could not enter the building

8. Joinery and kitchen

Installing cabinets and worktops

Measured on site after the walls are finished

9. Finishes

Paint, fixtures, lighting

The last trades before cleaning

10. Furniture and styling

Furniture, curtains, art

Delivered into a clean home


Why does planning come first?


Because every decision you postpone stops a team on site. In the M penthouse, all the planning and the orders from suppliers were closed in advance, so we could start the moment the keys were handed over. In the S apartment, we went into the works only after precise planning and after closing every detail, including ordering all the finishes and furniture, and there were no hard moments of crisis along the way.


The smoked oak kitchen of the S apartment, with tall cabinets, a light worktop and a peninsula with two gray bar stools.
The smoked oak kitchen of the S apartment, with tall cabinets, a light worktop and a peninsula with two gray bar stools.

Choosing finishes is part of planning, so ask the right questions before you sign; I listed them in my post on questions to ask in every showroom.


What happens at demolition?


Demolition shows what the drawings could not. The N apartment, in an old Tel Aviv building, was stripped completely, including the windows, the flooring and the old drywall ceilings, down to the shell. Until demolition, it was not clear which structural constraints would appear, and in practice we had to find creative solutions that were not in the original plan, with structural engineering advice. My recommendation: leave room in the schedule and in the decisions for this stage.


Why do infrastructure and ceilings come before floors?


Because pipes and wires run in the floor and the ceiling. In the N apartment, the new plumbing required raising the floor level, and descending concrete beams in the ceiling dictated the route of the air conditioning and the forced ventilation of the bathroom. In the S apartment, all the electrical wiring and plumbing were replaced, a new air-conditioning system was installed, and an 8 cm lowered ceiling across the home carries the infrastructure and the recessed lighting.


What can go wrong with the floors?


Logistics. In the N apartment, the tiles chosen first turned out to be too large to bring into the apartment, even with a crane, because of the building's constraints. We had to replace them with another option without harming the overall design. My recommendation: before ordering large tiles, slabs or a kitchen island, check the stairwell, the elevator and the access to the building.


A gray-violet joinery unit with a built-in TV standing in the middle of the N apartment, on a continuous light gray tiled floor.
A gray-violet joinery unit with a built-in TV standing in the middle of the N apartment, on a continuous light gray tiled floor.

When do joinery, furniture and styling come in?


Joinery and the kitchen are installed after the floors and walls are finished, so they fit exactly. Furniture, curtains and art come last. In the B apartment, a holiday apartment on the Tel Aviv promenade, the owners asked to keep the existing layout, and planning took two months and the works three. With no walls moved, the scope stayed limited and the process short.


The B apartment, with a dark kitchen and a white island with black bar stools, a herringbone oak floor and the sea through the windows beyond the dining table.
The B apartment, with a dark kitchen and a white island with black bar stools, a herringbone oak floor and the sea through the windows beyond the dining table.

For real timelines from my projects, see how long a renovation takes in Israel, and for a calmer process, my post on turning renovation challenges into design opportunities.


Frequently asked questions


What is the first step in a renovation?

Planning: the layout, the electrical and plumbing plans, the joinery and the finishes, followed by ordering.


Should I order materials before the works start?

Yes. In the S apartment, everything was ordered before the works began, and there were no moments of crisis.


Do floors go in before the kitchen?

Yes, as a rule. The kitchen and joinery are installed on the finished floor, so they fit exactly.


How do I deal with surprises during demolition?

Leave room in the schedule, keep the designer and contractor on site to decide quickly, consult a structural engineer when the structure is involved, and use licensed electricians and plumbers for the infrastructure.


Planning a renovation and want it to run in the right order? I'd love to hear about your project.


Maya Sheinberger is an interior designer with more than 18 years of experience. After five years at a leading architecture firm, she founded her independent studio in 2012. She holds a B.Des with honors from the College of Management. Her work has appeared in more than 170 publications in Israel and abroad, including eight Archilovers Best Project awards, and one of her apartments features in the book The New Minimalist Style.


S and N apartments: Photography @itaybenitphotographer · Styling @maya_livnat_harush. B apartment: Photography @itaybenitphotographer · Styling @ofri.paz

 
 